Site Final | 7/18/2017 | 7/18/2017 | 7/18/2017 | A | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 7/18/2017 | 7/18/2017 | 7/18/2017 | P | PASS |
Jim Sly
|
|
|
|
General Inspection | 6/16/2017 | 6/16/2017 | 6/16/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/1/2017 | 5/1/2017 | 5/1/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on interior and exterior. Trash containment good. Correction: sweep trackout.
|
General Inspection | 3/14/2017 | 3/14/2017 | 3/14/2017 | | PASS |
Melissa Jannusch
|
|
|
DI protection OK. Trash containment good. No trackout onto road. No corrections requested.
|
General Inspection | 1/25/2017 | 1/25/2017 | 1/30/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/8/2016 | 12/8/2016 | 12/8/2016 | | PASS |
Andy J. Long
|
|
|
Permit sign and SWPPP information posted for Dropzone Apartments. No significant trackout and winter safety sand is now on the road. No discharges or spills on or around site. Framing is now in progress and parking lot paved and onsite stormwater inlet installed, No corrections at this time
|
Site Preparation | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Andy J. Long
|
|
|
Colby Phone #: ###-####
Dropzone apartment grading and initial excavation conductied under main site permit ESC16-00696
Four 8-plex apartment buildings to be erected. Site access and parking not yet paved. Asphalt scheduled for 2nd week of November.
Reviewed ESC conditions with RP Colby, requested 4 or more trash containment bins and designated scrap wood and material staging zone with stabilized entrance. Surrounding storm drains have sediment filter bags installed for Dropzone Sub SFHs by CBH
Foundation construciton and vertical construction to start on Monday. Follow up inspection for construction entrance and washout facility on Monday 10/24 PM
|
Permit Ready to Issue | | | 10/13/2016 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 10/13/2016 | | DONE |
|
|
|
|
Application received | | | 5/20/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2016 9:53AM
|