Site Final | 5/15/2017 | 5/15/2017 | 5/15/2017 | P | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 5/15/2017 | 5/15/2017 | 5/15/2017 | | PASS |
Melissa Jannusch
|
|
|
Temporary BMPs are removed. Landscaping is complete. Okay to final.
|
General Inspection | 3/28/2017 | 3/28/2017 | 3/28/2017 | | PASS |
Melissa Jannusch
|
|
|
Vertical WIP. No trackout. Sediment contained on site. Perimeter controls ok. No corrections requested.
|
General Inspection | 2/10/2017 | 2/10/2017 | 2/10/2017 | | PASS |
Melissa Jannusch
|
|
|
No trackout, silt fence in place, no dirt on sidewalk surrounding project. No corrections
|
General Inspection | 12/21/2016 | 12/21/2016 | 12/27/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/3/2016 | 10/3/2016 | 10/3/2016 | P | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Perimeter sediment control silt fence and wattle installed. Permit sign posted. No violations observed. No foundation work has occuring yet.
|
Issue & PRINT permit COM | | | 9/21/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/2/2016 | | 6/2/2016 | | PASS |
Andy J. Long
|
|
|
ESC narrative and site map approved. Vallid PD and RP designated.
|
Application received | | | 5/27/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 27 2016 12:02PM
|