Site Final | 6/24/2016 | 6/24/2016 | 6/24/2016 | P | PASS |
Andy J. Long
|
|
|
Demo phase complete and all materials removed. No trackout or accumulations around perimeter. Work now covered with ESC16-00209
|
General Inspection | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | PASS |
Andy J. Long
|
|
|
check for dust control water truck
Must be on site or will need to stop. Site RP stated truck is on its way as of 11:00 AM
Water truck was brought to site as requested and utilized to control dust from loading the demolished materials into dump trucks.
Will continue to monitor site, no other corrections.
|
Complaint Inspection | 6/13/2016 | 6/13/2016 | 6/13/2016 | A | PART |
Andy J. Long
|
|
|
Complaint about loose insulation material surrounding site in grass and storm drains...
Inspected @ 10:45
RP Joe and I walked site perimeter. During demolition over weekend, wind did blow cellulose insulation material. RP stated that much of it was cleaned and streets swept.
All receiving MS4 and prviate stormwater drop inlets have filter fabric protection.
Correction Request - no water truck on site at time of inspection. Requested that water truck be on site for dust control asap and that loads should be covered or weighed down - rake up insulation material on grass - find complaint location and go clean up
Will check back this afternoon...
|
Issue & PRINT permit COM | | | 6/10/2016 | | DONE |
|
|
|
|
Application received | | | 6/9/2016 | | |
|
|
|
|
Routing - Erosion and Sediment | 6/9/2016 | | 6/9/2016 | | PASS |
Andy J. Long
|
|
|
Valid RP designated. ESC plan submitted and approved under BLD16-00473
|