General Inspection | 12/1/2017 | 12/1/2017 | 12/1/2017 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 12/1/2017 | 12/1/2017 | 12/1/2017 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/16/2017 | 10/16/2017 | 10/16/2017 | | CANC |
Andy J. Long
|
|
|
|
Site Final | 8/30/2017 | 8/31/2017 | 8/31/2017 | A | NR |
Andy J. Long
|
|
|
9:15 meeting with Layton Construction
Disturbed area around stormwater pond has been hydroseeded but no significant vegetation established.
Will continue to monitor.
Meet Layton contact Brent at Gowen Business Park. Site is set up for initial rough grading. Working without issued GRD or ESC. Issued fine for early start, will pay when pick up permit.
|
General Inspection | 8/28/2017 | 8/28/2017 | 8/30/2017 | | PEND |
Andy J. Long
|
|
|
swale/pond revegetation
|
General Inspection | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Melissa Jannusch
|
|
|
Sediment pond area is still in the revegetation stage and the soils are not fully stablized. The area appears to have been hydroseeded and mulched. very spare vegetation is growing currently. Will continue to inspect until the stormwater pond has establized vegetation.
|
Site Final | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | NR |
Melissa Jannusch
|
|
|
Not ready to final. Main building area soil is stable and no remaining temporary BMPs.
Sediment pond is not landscaped yet.
Stagging area on lot across street is going to be used for a future project.
Let RP know that ESC final will wait until after revegetation takes place but will not effect the certificate of ocupancy. Brent ###-####
|
General Inspection | 5/8/2017 | 5/8/2017 | 5/9/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on interior and exterior. Some areas are stabilized. WIP on the drainage pond. The soil is not stabilized in this area. Staging area and stockpiles are still active on the site across the street.
|
General Inspection | 3/21/2017 | 3/21/2017 | 3/21/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on interior and exterior. No trackout No ESC issues observed.
|
General Inspection | 1/31/2017 | 1/31/2017 | 1/31/2017 | | PASS |
Melissa Jannusch
|
|
|
Snow covered conditions. Met with Brent Conger on site. Majority of silt fence is in good conditions, wattles are in place, no track out, sign posted, pond looks good, visible DI bags are okay. Requested fix to silt fence once ground unthaws. WIP on building.
|
General Inspection | 12/9/2016 | 12/15/2016 | 12/21/2016 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2016 | 12/6/2016 | 12/9/2016 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2016 | 11/25/2016 | 11/25/2016 | A | PART |
Andy J. Long
|
|
|
WIP. Permit sign posted, no trackout. Perimter wattles and silt fence installed along Beachcraft Street.
Correction request: - do mainteanance on DI bag at end of culdesac.
|
General Inspection | 10/13/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Andy J. Long
|
|
|
WIP on foundation on Beechcraft buidling. Silt fence perimeter is installed on the north and west side of site. Receiving DI has sediment bag protection with good capacity.
RP onsite, stated today they will be installing wattle today in between the two sections of silt fence. I also requested they shovel accumulated silt trapped outside of DI bag.
No trackout, fugitive dust or discharges. Permit sign and SWPPP info posted.
|
BMP Violation | 8/26/2016 | 8/26/2016 | 8/26/2016 | P | PART |
Andy J. Long
|
|
|
No onsite dust control water truck or alternative during grading and hauling operation. No other issues and RP on site. Tuffy still sharing water truck between sites.
I requested that a full time water truck be on site during this type of activity.
RP Brent called water truck and stated it is on way.
Second visit when no water truck on site....
|
General Inspection | 8/25/2016 | 8/25/2016 | 8/25/2016 | P | PASS |
Evan Jenkins
|
|
|
|
Site Preparation | 8/11/2016 | 8/11/2016 | 8/11/2016 | P | PASS |
Andy J. Long
|
|
|
Brent Phone #: ###-####
Site BMPs are installed and initial grading and and import of fill is occuring. Inlet protection, construction entrance, and silt fence perimeter are installed. Permit, RP, and ESC plan are on site.
Tuffy has one water truck servicing multiple sites in the area. At this time, the truck comes and waters the haul loop 1-2x per hour and it appears to be sufficient - no significant or continuous dust plumes leaving site. I requested that a full time truck be onsite if dust increases.
|
Issue & PRINT permit COM | | | 8/10/2016 | | DONE |
|
|
|
|
Application received | | | 6/23/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 23 2016 9:01AM
|
Routing - Erosion and Sediment | 6/23/2016 | | 6/23/2016 | | PASS |
Andy J. Long
|
|
|
Reviewed with BLD16-02176 application. Same project with seperate GRD and BLD permits, and only one ESC permit. Site preparation inspection REQUIRED, call ###-####
ESC plan approved.
|