Site Final | 11/28/2016 | 11/28/2016 | 11/28/2016 | A | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 11/28/2016 | 11/28/2016 | 11/28/2016 | P | PASS |
Jim Sly
|
|
|
|
Site Final | 10/10/2016 | 10/26/2016 | 10/26/2016 | P | NR |
Andy J. Long
|
|
|
SFH near completion. Landscaping/stabilization not yet installed. Temp BMP DI bag is installed. Trash container onsite. No violations
|
General Inspection | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on interiior. Permit sign posted, no significant trackout. Site Final scheduled for 10/26
TKO homes to sweep up gutter and clean around inlets before removing DI bags on west end of Woodland. Evergreen Homes has been requested to remove temp DI bags on east end of Woodland.
|
Site Preparation | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | PASS |
Evan Jenkins
|
|
|
TJ Phone #: ###-####
Permit Posted along with a concrete washout now onsite. Curb was swept last night, sidewalk and road will be swept today. Approved for construction
|
Site Preparation | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | NR |
Evan Jenkins
|
|
|
Taron Phone #: ###-####
Permit not Posted, No Concrete Washout Curb and sidewalk Attempted to call RP Taron and got VM
|
Permit Ready to Issue | | | 8/1/2016 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 8/1/2016 | | DONE |
|
|
|
|
Application received | | | 7/21/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 21 2016 1:22PM
|