Site Final | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 11/8/2016 | 11/9/2016 | 11/9/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on new gas station. No loose sediment or other material leaving site. Perimeter and inlet sediment controls installed. No trackout, rumblebars installed. Permit signa and SWPPP info posted. Approved.
|
Site Preparation | 10/19/2016 | 11/8/2016 | 11/8/2016 | A | CANC |
Andy J. Long
|
|
|
data entry error, rescheduled 11/9
|
General Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 | P | PASS |
Andy J. Long
|
|
|
ESC walk through inspection and conference with Project Superindentant Chris with ESC.
No discharges, trackout, uncontained trash or fugitive dust occuring. ESC BMPs are installed including: - permit posting and SWPPP info at construction entrance - trackout control with rumble bars and preservation of pre-existing asphalt during initial phase. - perimeter sediment control wattles at potential sheet flow runoff points. Wattles installed around temporary stockpile - drop inlet sediment protection installed. Note: no installation on MS4 system or ROW - ESCP and SWPPP binder onsite and updated
Site is in compliance, no corrective actions requested at this time.
|
Issue & PRINT permit COM | | | 10/6/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/26/2016 | | 9/26/2016 | | DONE |
Andy J. Long
|
|
|
ESC plan approved. Valid RP designated.
|
Application received | | | 8/4/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 4 2016 4:10PM
|