Site Final | 2/7/2017 | 2/8/2017 | 2/9/2017 | P | PASS |
Andy J. Long
|
|
|
Slope stabilizing erosion control blanket is installed well and functioning. Grass is starting to grow on slope. Homeowner and neighbor in agreement to leave temporary silt fences until chain link fence is installed later in spring time. Need to leave the erosion control blanket in place to bio-degrade. No erosion issues or sediment/mud leaving property. No further corrections or requests.
|
General Inspection | 10/18/2016 | 10/18/2016 | 10/18/2016 | P | PASS |
Andy J. Long
|
|
|
Restoration/repair work is complete. Sediment and erosion controls installed on hillside to stabilze include two silt fences, erosion control blanket, and wattles. Does not look like the hillside has any vegetation coming in under blanket at this time.
|
Random Inspection | 9/1/2016 | 9/1/2016 | 9/1/2016 | A | FAIL |
Evan Jenkins
|
|
|
check restoration progress
Home owner has not hired a cleanup crew for cleanup from damage to neighbors property. ESC RP Andy stated home owner has not hired them for cleanup. According to RP Andy, a Large retaining wall will be installed, which will require a BLD and GRD for this work. Called both Jason Taylor and Bob A. to report info and left both VM's on new information for work that will occure.
|
BMP Violation | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | CANC |
Evan Jenkins
|
|
|
Data Entry Error
|
Routing - Erosion and Sediment | 8/30/2016 | | 8/30/2016 | | PASS |
Evan Jenkins
|
|
|
Emergency Repair work from broken sprinkler system.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 8/30/2016 | | DONE |
|
|
|
all requirements met
|
Issue & PRINT permit SFD | | | 8/30/2016 | | DONE |
|
|
|
|
Site Preparation | 8/26/2016 | 8/26/2016 | 8/26/2016 | A | PASS |
Evan Jenkins
|
|
|
Restoration work has begun by Syman Co. Full crew working hard on cleanup and BMP installation
|
Application received | | | 8/26/2016 | | |
|
|
|
|
Issue & PRINT permit SFD | | | 8/26/2016 | | DONE |
|
|
|
|