Site Final | 3/15/2017 | 3/15/2017 | 3/15/2017 | P | PASS |
Melissa Jannusch
|
|
|
Landscaping complete. Soil stable. Okay to final.
|
Site Preparation | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | PASS |
Andy J. Long
|
|
|
Weston Phone #: ###-####
Subdivision BMPs installed. Approved for construction.
|
Site Preparation | 9/15/2016 | 9/16/2016 | 9/15/2016 | A | PASS |
Evan Jenkins
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
Approved for construction
|
Site Preparation | 9/15/2016 | 9/19/2016 | 9/15/2016 | A | CANC |
Evan Jenkins
|
|
|
Phone #: ###-#### >> Inspection requested via web by Weston Wagner Inspection cancelled from web by: Weston Wagner
|
Issue & PRINT permit SFD | | | 9/14/2016 | | DONE |
|
|
|
|
Application received | | | 8/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2016 3:21PM
|