Site Final | 3/9/2017 | 3/10/2017 | 3/10/2017 | A | PASS |
Andy J. Long
|
|
|
The project is located within a secured area. If you need access please call me 30 prior to the inspection and I can escort you in the area. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
No ESC requests. Project complete, conditions satisfied.
|
Site Preparation | 11/30/2016 | 12/1/2016 | 12/1/2016 | A | PASS |
Andy J. Long
|
|
|
The site is located within a secure area. I will escort you into the area but you will have to call me 30 minutes prior to the inspection. Thanks Andy. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
Reviewed ESC plan with RP. Onsite storm drains have sediment protection. Crew has ESC training.
BLD inspector to observe ESC conditions during structural inspections
Approved
|
Permit Ready to Issue | | | 11/28/2016 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 11/28/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 11/4/2016 | | 11/4/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan submitted and approved. Valid PD and RP desingated.
|
Application received | | | 9/7/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 7 2016 4:36PM
|