Site Final | 10/24/2017 | 10/26/2017 | 10/26/2017 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/24/2017 | 10/24/2017 | 10/24/2017 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 10/9/2017 | 10/9/2017 | 10/10/2017 | | CANC |
Michael Zawacki
|
|
|
Needs house keeping. Wattles are worn, DI bags need to be removed, emptied, and reinstalled. Some trackout but none is leaving site. Floor coting and roof material buckets were stored next to storm drain. Some loose trash. Site is self contained.
|
General Inspection | 9/22/2017 | 9/22/2017 | 9/22/2017 | | PASS |
Andy J. Long
|
|
|
No discharges or trackout. Trash contained. No corrections for North Hill subdivision
|
General Inspection | 9/7/2017 | 9/7/2017 | 9/8/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/23/2017 | 8/23/2017 | 8/24/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/8/2017 | 8/8/2017 | 8/8/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/24/2017 | 7/24/2017 | 7/24/2017 | | CANC |
Andy J. Long
|
|
|
See ESC 15-00853
|
General Inspection | 6/30/2017 | 6/30/2017 | 6/30/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/14/2017 | 6/14/2017 | 6/15/2017 | | CANC |
Andy J. Long
|
|
|
see ESC15-00853 for inspection activity at North Hill subdivision. This is individual townhome permit
|
Site Preparation | 12/12/2016 | 12/12/2016 | 12/12/2016 | P | PASS |
Andy J. Long
|
|
|
Approved for construction. Subdivision storm drains have inlet protection, frontage landscaping is now completed.
See also main North Hill subdivision permit ESC15-00853 for corrections currently in progress.
|
Issue & PRINT permit SFD | | | 11/10/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/12/2016 | | 10/12/2016 | | DONE |
Andy J. Long
|
|
|
Subdivision BMPs and onsite trash and concrete washout facility shall be provdided and maintained. Valid PD designated Note : RP is a certified program ESC Training Instructor (RP&PD)
|
Application received | | | 9/26/2016 | | |
|
|
|
|