Site Final | 3/8/2017 | 3/8/2017 | 3/9/2017 | P | PASS |
Andy J. Long
|
|
|
Project is complete. The land owner is responsible for re-paving. All areas are stabilized with road mix at this time. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
No materials or temp BMPs related remaining from IPC phase of project for Fairview & Cole. Knife River working on intersection in ROW areas. No further inspections required on this permit, conditions satisfied.
|
Site Preparation | 11/3/2016 | 11/3/2016 | 11/3/2016 | P | PASS |
Andy J. Long
|
|
|
Andy call me 30 minutes prior to your inspection if you want me to meet you there. They are working at night so you probably won''t see anyone there. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
Idaho Power work approved.
|
Issue & PRINT permit COM | | | 10/10/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/4/2016 | | DONE |
|
|
|
|
Telephone call | | | 10/4/2016 | | DONE |
|
|
|
emialed Eldon that his permit is ready
|
Routing - Erosion and Sediment | 9/30/2016 | | 10/3/2016 | | DONE |
Andy J. Long
|
|
|
ESC plan approved. Valid PD & RP. Site preparation inspection required.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2016 | | DONE |
|
|
|
|
Application received | | | 9/30/2016 | | |
|
|
|
|