General Inspection | 6/15/2018 | 6/15/2018 | 6/15/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 4/30/2018 | 4/30/2018 | 4/30/2018 | | PASS |
Michael Zawacki
|
|
|
Exterior work and landscaping complete. Site is clean. Section of parking lot still fenced off for storage, trash, and restrooms.
|
Site Final | 3/9/2018 | 3/14/2018 | 3/14/2018 | A | NR |
Michael Zawacki
|
|
|
Job trailer and fenced off storage still on site, dumpster in storage area. Blocksome still on DIs in parking lot.
|
General Inspection | 3/9/2018 | 3/9/2018 | 3/9/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/22/2018 | 1/22/2018 | 1/22/2018 | | PASS |
Michael Zawacki
|
|
|
Work on exterior completed. All landscaping in place and site is stable. Inlet protection still installed in DI on traffic island at Park & Park Center. Job trailer and fenced staging area still on site.
|
Site Final | 11/21/2017 | 12/6/2017 | 12/6/2017 | A | NR |
Michael Zawacki
|
|
|
Job trailer and dumpster still on site. Blocksome installed in parking lot. Pallet of rebar still in parking lot. Landscaping is complete.
|
Site Final | 11/21/2017 | 11/21/2017 | 11/21/2017 | A | NR |
Andy J. Long
|
|
|
Not ready for final. Some onsite landscaping work still in progress. Dumpster, concrete washout, job trailer still onsite.
MS4 DI bags have been removed due to onsite stormwater retention and parking lot stabilization. Will check back for Site Final in December.
|
Random Inspection | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PASS |
Michael Zawacki
|
|
|
In process of installing sod and bark. Site contained.
|
General Inspection | 10/11/2017 | 10/11/2017 | 10/12/2017 | | PASS |
Michael Zawacki
|
|
|
Site clean. Disturbed area is contained. Some discoloration on road but no loose trackout. Curb and gutters clean, DIs clean. Dumpster in use, site free of loose trash. Plastic sheeting being used to keep dust inside building. Very little dirt on side entrance but visible broom marks.
|
General Inspection | 8/23/2017 | 8/25/2017 | 8/25/2017 | A | PART |
Andy J. Long
|
|
|
Sweep up Walnut sidewalk and gutter...
|
Complaint Inspection | 8/23/2017 | 8/23/2017 | 8/23/2017 | P | PEND |
Andy J. Long
|
|
|
dust
No fugitive dust plumes leaving site at time of inspection. Water truck onsite. Park Blvd currently being resurfaced, so lots of disturbed area around site. No discharges or spills observed. Will continue to monitor this week.
|
General Inspection | 7/25/2017 | 7/25/2017 | 7/25/2017 | A | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/26/2017 | 5/26/2017 | 5/26/2017 | A | PASS |
Andy J. Long
|
|
|
Foundation and initial frame work occuring. Site perimeter existing sidewalk and curbing has contained sediment. Solid construction entrance installed, no trackout. Permit sign posted by job trailer.
|
Random Inspection | 4/21/2017 | 4/21/2017 | 4/21/2017 | A | PASS |
Andy J. Long
|
|
|
WIP on foundations. Exisitng hardscape and vegetation at perimeter has been installed. MS4 inlets have sediment filter bags installed. No trackout, fugitive dust, or discharges observed.
|
General Inspection | 3/10/2017 | 3/15/2017 | 3/15/2017 | A | PASS |
Melissa Jannusch
|
|
|
No ESC issues observed. No trackout.
|
Site Preparation | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Andy J. Long
|
|
|
Call hour to meet // Jill Phone #: ###-####
Perimeter BMPs installed (inlet protection, wattles on west end of project. Plan is to preserve existing parking lot surface and curbing for stabilized construction access on south end of project. Permit sign and CGP NOI posted.
Notified project managers about trackout, dewatering, and fugitive dust regulations.
Approved to start.
|
Issue & PRINT permit COM | | | 3/1/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 12/16/2016 | | 12/16/2016 | | DONE |
Andy J. Long
|
|
|
ESC site map and SWPPP narrative approved. Valid PD and RP designated. Site preparation inspection required ###-####
|
Application received | | | 11/30/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 30 2016 2:30PM
|