Site Final | 11/15/2017 | 11/16/2017 | 11/16/2017 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 11/15/2017 | 11/15/2017 | 11/15/2017 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 10/31/2017 | 10/31/2017 | 10/31/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/12/2017 | 10/12/2017 | 10/13/2017 | | PASS |
Michael Zawacki
|
|
|
Gator guard intact. Washout dug and used.Trash being thrown away. Free of trackout.
|
General Inspection | 9/15/2017 | 9/15/2017 | 9/19/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/31/2017 | 8/31/2017 | 8/31/2017 | | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 2/15/2017 | 3/1/2017 | 2/28/2017 | A | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 2/22/2017 | 2/22/2017 | 2/22/2017 | P | PASS |
Melissa Jannusch
|
|
|
Trackout cleaned. Sign posted
|
Site Preparation | 2/14/2017 | 2/14/2017 | 2/15/2017 | P | PEND |
Melissa Jannusch
|
|
|
John Phone #: ###-#### Subdivision BMPs are installed, concrete washout is ready. Corrections requested: Sweep up trackout Post sign
|
Permit Ready to Issue | | | 2/3/2017 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 2/3/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 12/27/2016 | | 12/27/2016 | | DONE |
Andy J. Long
|
|
|
ESC plan with narrative and site map. Valid RP and PD designated.
|
Application received | | | 12/20/2016 | | |
|
|
|
|