Site Final | 3/7/2018 | 3/9/2018 | 3/12/2018 | P | PASS |
Andy J. Long
|
|
|
enter via Pamela Baker Park.
Work complete for project. No ESC requests or corrections.
|
Aging Inspection | 3/6/2018 | 3/6/2018 | 3/7/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/3/2018 | 1/3/2018 | 1/3/2018 | P | PASS |
Michael Zawacki
|
|
|
|
Aging Inspection | 12/21/2017 | 12/21/2017 | 12/21/2017 | | PASS |
Michael Zawacki
|
|
|
Inspected 12-19. No issues.
|
General Inspection | 10/20/2017 | 10/20/2017 | 10/24/2017 | P | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 5/24/2017 | 5/24/2017 | 5/26/2017 | P | CANC |
Melissa Jannusch
|
|
|
|
Issue & PRINT permit COM | | | 2/7/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/3/2017 | | 2/3/2017 | | PASS |
Melissa Jannusch
|
|
|
BMPs include: staging area, stabilized construction entrance, concrete washout, and a fiber wattle along the access road. Ensure channel bank stabilization is reached.
|
Application received | | | 1/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 17 2017 9:59AM
|