General Inspection | 10/23/2017 | 10/23/2017 | 10/24/2017 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 10/24/2017 | 10/24/2017 | 10/24/2017 | P | PASS |
Michael Zawacki
|
|
|
|
Complaint Inspection | 7/18/2017 | 7/18/2017 | 7/19/2017 | P | PASS |
Melissa Jannusch
|
|
|
Grading is contained to lot. Fence okay and soil is continaed on site. Ensure the area is fully landscaped before ESC site final.
DI bag okay. Trash contained.
|
Site Preparation | 3/15/2017 | 3/15/2017 | 3/15/2017 | P | NR |
Melissa Jannusch
|
|
|
Not ready to start. No BMPs installed. Needs inlet protection, perimeter controls, and entrance. Spoke with RP. Excavator will install controls before starting work. He will call once the controls are implemented. Sign is posted.
|
Issue & PRINT permit SFD | | | 3/13/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/15/2017 | | 2/15/2017 | | PASS |
Melissa Jannusch
|
|
|
New Duplex. BMPs. Inlet protection, construction entrance (on Boise Ave), 2 sand filled drainage windows protected with wattles, silt fence along perimeter of site, concrete washout, sand/gravel burlap bar or fiber wattle placed in the gutter flow line. Swales are around the sides and back of the property, sand/ gravel bags or fiber wattles are to be placed in the swale flow line.
|
Application received | | | 2/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 8 2017 1:15PM
|