Site Final | 4/14/2017 | 4/20/2017 | 4/21/2017 | P | PASS |
Melissa Jannusch
|
|
|
Not ready for a site final. WIP on foundation. Sign is posted. No trackout. No trash arounds site. Project ok. No corrections requested.
|
General Inspection | 3/31/2017 | 4/14/2017 | 4/14/2017 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/28/2017 | 3/30/2017 | 3/31/2017 | P | PART |
Andy J. Long
|
|
|
WIP on foundation. No trackout or discharges occuring. Permit sign posted in alley. Access to site from ally.
Request to install inlet protection on north side Sloan at Utahna. Requested that site foreman Rob take the RP class.
|
Site Preparation | 3/27/2017 | 3/28/2017 | 3/28/2017 | A | PASS |
Andy J. Long
|
|
|
Rob Phone #: ###-####
|
Issue & PRINT permit SFD | | | 3/21/2017 | | DONE |
|
|
|
|
Application received | | | 2/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 17 2017 1:57PM
|