General Inspection | 4/12/2018 | 4/12/2018 | 4/12/2018 | | PASS |
Andy J. Long
|
|
|
Home complete, landscaped and occupied. Adajecent lot has been cleaned. Parcel under review for development.
|
DOC - Permit Finaled | 4/12/2018 | 4/12/2018 | 4/12/2018 | P | PASS |
Andy J. Long
|
|
|
|
Conference | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | CANC |
Andy J. Long
|
|
|
|
Conference | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | PEND |
Andy J. Long
|
|
|
Request to stabilize adjacent lot and pull 1st down stream DI bag from site. Notified that ESC permit is still open and needs site final.
|
Complaint Inspection | 3/16/2018 | 3/19/2018 | 3/19/2018 | P | DONE |
Andy J. Long
|
|
|
No issues on this site. Some sediment runoff and minor erosion occuring on open lots on west side of Mockbee. Corrections pending.
|
General Inspection | 3/13/2018 | 3/13/2018 | 3/13/2018 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 2/26/2018 | 2/26/2018 | 2/26/2018 | | PASS |
Michael Zawacki
|
|
|
Home appears completed and landscaping istalled. No issues.
|
General Inspection | 2/9/2018 | 2/9/2018 | 2/9/2018 | | PASS |
Michael Zawacki
|
|
|
Yard landscaped and waiting for final stabalization.
|
General Inspection | 1/25/2018 | 1/25/2018 | 1/26/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/10/2018 | 1/10/2018 | 1/11/2018 | | PASS |
Michael Zawacki
|
|
|
Exterior work and landscaping complete.
|
General Inspection | 12/21/2017 | 12/21/2017 | 12/21/2017 | | PASS |
Michael Zawacki
|
|
|
Yard has been landscaped. No issues observed.
|
General Inspection | 12/6/2017 | 12/6/2017 | 12/6/2017 | | PASS |
Michael Zawacki
|
|
|
Exterior work completed.
|
General Inspection | 11/17/2017 | 11/17/2017 | 11/17/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/2/2017 | 11/2/2017 | 11/2/2017 | | PASS |
Michael Zawacki
|
|
|
Home complete. Yard landscape and stabalized.
|
Site Preparation | 3/24/2017 | 3/27/2017 | 3/27/2017 | A | PASS |
Melissa Jannusch
|
|
|
Okay to start. Talked with RP about using concrete washout once concrete work begins and implementing daily sweeping while muddy conditions persist.
|
Permit Ready to Issue | | | 3/24/2017 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 3/24/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/8/2017 | | 3/8/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Notified GC need to provide valid RP
|
Application received | | | 2/23/2017 | | |
|
|
|
|