Site Final | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PASS |
Andy J. Long
|
|
|
Home complete, landscaped and occupied. No trash or building debris left behind on adjacent lots. Temp BMPs to remain Heartleaf during active SFH construction.
|
Site Final | 10/12/2017 | 10/19/2017 | 10/24/2017 | A | DONE |
Michael Zawacki
|
|
|
|
Site Final | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PEND |
Michael Zawacki
|
|
|
Area ready for grass. Sod on site but not installed. Will check again.
|
General Inspection | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PART |
Melissa Jannusch
|
|
|
Trash containment needed on site.
|
Site Preparation | 5/9/2017 | 5/9/2017 | 5/9/2017 | A | PASS |
Melissa Jannusch
|
|
|
Okay to start. Silt fence installed correctly. Talked with RP on site about ESC requirements.
Dave: ###-####
|
Issue & PRINT permit SFD | | | 5/1/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/4/2017 | | 4/4/2017 | | PASS |
Andy J. Long
|
|
|
ESC site map with narrative approved. Site preparation inspection required, call ###-####
|
Application received | | | 3/24/2017 | | |
|
|
|
|