Aging Inspection | 2/4/2019 | 2/4/2019 | 2/4/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | PASS |
Michael Zawacki
|
|
|
All disturbances completed, still work inside building. Outside is complete and lanscaped.
|
General Inspection | 12/3/2018 | 12/11/2018 | 12/11/2018 | A | PASS |
Michael Zawacki
|
|
|
No disturbances.
|
Aging Inspection | 12/3/2018 | 12/3/2018 | 12/4/2018 | | PASS |
Michael Zawacki
|
|
|
Outside work complete.
|
General Inspection | 10/1/2018 | 10/1/2018 | 10/1/2018 | | PASS |
Michael Zawacki
|
|
|
Lot is landscaped and parking lot complete. OK to final when building permit closed.
|
General Inspection | 7/30/2018 | 7/30/2018 | 7/30/2018 | | PASS |
Michael Zawacki
|
|
|
Lot is stripped and ready for landscaping. Forms are being placed in rear for parking lot.
|
General Inspection | 5/28/2018 | 5/28/2018 | 5/29/2018 | | PASS |
Michael Zawacki
|
|
|
Work is in interior. Only disturbed area is gravel lot in back.
|
General Inspection | 3/27/2018 | 3/27/2018 | 3/27/2018 | | PASS |
Michael Zawacki
|
|
|
Only exposed area is in rear parking off alley. No issues.
|
General Inspection | 1/25/2018 | 1/25/2018 | 1/25/2018 | | PART |
Michael Zawacki
|
|
|
Rear of property muddy. There is some mud going into alley. No perimeter controls but mud isn't going onto sidewalk. Building is currently boarded up an access is through rear.
|
(F) Reprint permit | | | 11/14/2017 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/19/2017 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 6/19/2017 | | DONE |
|
|
|
|
Application received | | | 4/6/2017 | | |
|
|
|
|
Routing - Erosion and Sediment | 4/6/2017 | | 4/6/2017 | | DONE |
Melissa Jannusch
|
|
|
Waiver letter approved
|