Site Final | 8/7/2018 | 8/7/2018 | 8/7/2018 | A | PASS |
Andy J. Long
|
|
|
Kevin w/ ESI
Building complete. Surrounding landscaping and pathways are installed. Grass is growing well. No temporary BMPs left onsite. Some minor work conducted by Timberline facility staff next to the trailor.
ESC permit conditions satisfied.
|
General Inspection | 8/6/2018 | 8/6/2018 | 8/7/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/19/2018 | 6/19/2018 | 6/20/2018 | | PASS |
Michael Zawacki
|
|
|
Addition construction looks complete. Landscapers are working on exterior west side of building. Dumpster still on site. No trackout or dust issues. No ESC issues.
|
General Inspection | 5/4/2018 | 5/4/2018 | 5/7/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/19/2018 | 3/19/2018 | 3/20/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/29/2018 | 1/30/2018 | 1/30/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on school addition, footprint constructed, vertical and interior work in progress. No trackout or loose debris in Timberline parking lot. Site perimeter is clean. No ESC corrections requested.
|
General Inspection | 1/25/2018 | 1/25/2018 | 1/29/2018 | | CANC |
Andy J. Long
|
|
|
|
Issue & PRINT permit COM | | | 6/20/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/19/2017 | | 4/19/2017 | | DONE |
Andy J. Long
|
|
|
ESC plan with site map and narrative approved. Valid PD, need to designate RP at time of permit issue. Site preparation and BMP installation required prior to construction. Call ###-#### to schedule.
|
Application received | | | 4/10/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 10 2017 2:49PM
|