Site Final | 9/28/2017 | 10/5/2017 | 10/10/2017 | P | PASS |
Andy J. Long
|
|
|
DI bag on Oakland and Belmont has been removed. DI bag on Oakland and Beacon shall be removed by project across street.
Disturbed area stabilized, temp BMPs removed. ESC permit finaled.
|
Site Final | 9/25/2017 | 9/26/2017 | 9/28/2017 | P | NR |
Andy J. Long
|
|
|
pat ###-####
confirm removal of temp BMPs
DI bag still installed on MS4 drains @ sw inlet of oakland/belmont. This drain is clogged. RP stated they will attempt again to remove. Will notify ACHD.
DI bag on Beacon and Oakland on NW corner should be removed.
|
General Inspection | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Andy J. Long
|
|
|
WIP on final landscaping. DI bag installed at northeast corner of site on Oakland will need to be removed. Staging across street is for the Oakland apartments project. No corrections requested.
|
Issue & PRINT permit COM | | | 5/5/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/2/2017 | | 5/4/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan with site map approved. Valid RP designated. Site preparation inspection required.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/4/2017 | | DONE |
|
|
|
|
Telephone call | | | 5/4/2017 | | DONE |
|
|
|
Spoke with Pat informing him that this permit is ready and the fee amount due for issuance
|
Application received | | | 5/2/2017 | | |
|
|
|
|