General Inspection | 2/28/2018 | 2/28/2018 | 2/28/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/27/2017 | 10/27/2017 | 10/27/2017 | P | PASS |
Michael Zawacki
|
|
|
Site below grade, no material can get off. DIs clean. No washout on site, says they have drivers bring it back with them.
|
General Inspection | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | PASS |
Andy J. Long
|
|
|
Very clean site. BMPs installed and maintained. No corrections needed.
|
General Inspection | 6/27/2017 | 6/27/2017 | 6/27/2017 | A | PASS |
Andy J. Long
|
|
|
WIP o excavation of foundation. BMPs installed:
-ESC permit sign posted with SWPPP info -rock construction entrance - DI sediment protection - water truck on site for dust supression
No violations observed. Approved.
|
Site Preparation | 6/7/2017 | 6/12/2017 | 6/12/2017 | A | PASS |
Andy J. Long
|
|
|
9:00 AM Jake Miller ###-####
ESC plan and SWPPP onsite. RP and excavation crew attended pre-construction site meeting. Permit sign posted. Silt fence properly installed along the downslope north construction limit. Will be hauling off dirt, will install angular rock construction entrance to replace existing small rock tracking pad. MS4 sediment protection installed on Executive. Notified crew of concrete washout, fugitive dust, and trash containment requirements.
Approved for constructon.
|
Issue & PRINT permit COM | | | 6/6/2017 | | DONE |
|
|
|
|
Application received | | | 5/10/2017 | | |
|
|
|
|
Routing - Erosion and Sediment | 5/10/2017 | | 5/10/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved, valid stormwater team designated. Site preparation inspection is REQUIRED, call ###-#### to schedule.
|