Site Final | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Jim Sly
|
|
|
|
General Inspection | 5/23/2018 | 5/23/2018 | 5/23/2018 | | PASS |
Michael Zawacki
|
|
|
All work completed. Building permit still open.
|
General Inspection | 5/8/2018 | 5/8/2018 | 5/9/2018 | | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 1/29/2018 | 1/29/2018 | 1/29/2018 | A | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PASS |
Michael Zawacki
|
|
|
Ground and concrete work complete. Currently working on frame.
|
General Inspection | 8/3/2017 | 8/18/2017 | 8/23/2017 | A | PASS |
Andy J. Long
|
|
|
Permit sign posted. No trackout or issues. Long existing driveway is preserved. No DI bag request due to large drainage area of this inlet.
|
General Inspection | 8/3/2017 | 8/7/2017 | 8/14/2017 | A | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 8/3/2017 | 8/3/2017 | 8/3/2017 | P | PASS |
Andy J. Long
|
|
|
Ren Phone #: ###-####
Construction area is down long (50m +) access driveway from Shenandoah. RP installed silt fence to prevent runoff to neighbors and DI protection on street. Approved for construction.
|
Permit Ready to Issue | | | 8/3/2017 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 8/3/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/9/2017 | | 6/9/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan with site map approved. Valid PD, RP to be determined by contractor. Site preparation inspection required, call ###-####
|
Application received | | | 6/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2017 11:45AM
|