Site Final | 7/11/2018 | 7/17/2018 | 7/17/2018 | A | PASS |
Andy J. Long
|
|
|
Project complete. Disturbed area stabilized with retaining walls and landscaping. ESC permit conditions satisfied.
|
Site Final | 6/26/2018 | 7/10/2018 | 7/11/2018 | A | NR |
Andy J. Long
|
|
|
|
General Inspection | 6/26/2018 | 6/26/2018 | 6/26/2018 | | PASS |
Andy J. Long
|
|
|
|
Fees Due Hold | 5/3/2018 | | 5/7/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/9/2018 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 1/8/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 12/20/2017 | | 12/20/2017 | | PASS |
Andy J. Long
|
|
|
|
Routing - Erosion and Sediment | 8/8/2017 | | 8/8/2017 | | FAIL |
Andy J. Long
|
|
|
Site map submitted, no project narrative. Please refer to the ESC plan checklist and ESC plan template for guidance.
http://pds.cityofboise.org/home/documents/apps/700/
|
Application received | | | 7/26/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 26 2017 9:28AM
|