Site Final | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PASS |
Andy J. Long
|
|
|
No disturbed area or loose material at site. No DI bags in MS4 inlets. All permits finaled.
|
General Inspection | 9/25/2018 | 9/25/2018 | 9/25/2018 | | PASS |
Michael Zawacki
|
|
|
Most exterior work completed. Jumptime is storing materials on sidewalk.
|
General Inspection | 7/25/2018 | 7/25/2018 | 7/25/2018 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on interior. Located next to CVS site, see ESC17-01011. No spills, dust, or other violations observed, permit posted on SLBS job trailer in front old Hastings.
|
Issue & PRINT permit COM | | | 4/13/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/18/2017 | | 9/18/2017 | | DONE |
Andy J. Long
|
|
|
ESC plan approved. Need to designated certified onsite ESC Responsble Person.
|
Application received | | | 9/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 8 2017 4:38PM
|