Site Final | 4/26/2018 | 4/26/2018 | 4/26/2018 | P | PASS |
Andy J. Long
|
|
|
Work complete. All disturbed areas landscaped and stabilized. No temporary BMPs left behind. ESC permit finaled.
BLD for project is still open
|
General Inspection | 10/13/2017 | 10/17/2017 | 10/19/2017 | A | PASS |
Andy J. Long
|
|
|
Perimeter wattles and silt fence installed. No trackout or sediment runoff. Permit sign posted. Status on requirement of GRD pending. No ESC violations, clean site.
|
General Inspection | 10/10/2017 | 10/11/2017 | 10/13/2017 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/2/2017 | 10/4/2017 | 10/10/2017 | A | CANC |
Andy J. Long
|
|
|
|
Site Preparation | 9/12/2017 | 9/14/2017 | 9/14/2017 | P | PASS |
Andy J. Long
|
|
|
Justin Phone #: ###-####
Perimeter wattles and silt fence installed. Permit sign posted.
Checking on remaining grading permit(s) needed for driveway and major landscaping project.
|
Permit Ready to Issue | | | 9/12/2017 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 9/12/2017 | | DONE |
|
|
|
|
Application received | | | 9/11/2017 | | |
|
|
|
|
Routing - Erosion and Sediment | 9/11/2017 | | 9/11/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan for pool construction only approved. RP for Gem Gunite designated. Valid PD. Site preparation inspection required to inspect BMPs for pool project.
|