General Inspection | 9/19/2018 | 9/19/2018 | 9/20/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 9/4/2018 | 9/4/2018 | 9/4/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/17/2018 | 8/17/2018 | 8/17/2018 | | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PASS |
Michael Zawacki
|
|
|
Clint Phone #: ###-#### Starting to layout and stake area for foundation. Site has berm behind that shouldn't be disturbed. Hillside is vegetated. Backfill will be kept on lot. Only concern will be watching for trackout.
|
(F) Reprint permit | | | 2/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/15/2018 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 2/15/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/17/2017 | | 10/17/2017 | | PASS |
Michael Zawacki
|
|
|
BMPs need to follow approved map. RP & PD good. Site prep required.
|
Application received | | | 10/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 13 2017 11:13AM
|