General Inspection | 1/22/2019 | 1/22/2019 | 1/22/2019 | | PASS |
Andy J. Long
|
|
|
see ESC 17-01687 for all remaining inspections for this site.
|
DOC - Permit Finaled | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/3/2019 | 1/3/2019 | 1/3/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 12/13/2018 | 12/13/2018 | 12/13/2018 | | PART |
Michael Zawacki
|
|
|
Met with RP while on site. Lined washout has ripped, some washout leaching out bottom. Trackout onto Ash St, has been cleaning at end of day.
|
General Inspection | 11/28/2018 | 11/28/2018 | 11/28/2018 | | PASS |
Michael Zawacki
|
|
|
Site is contained. Will need to monitor for trackout, few trucks and trailers parking in site, all others on street parking.
|
General Inspection | 11/13/2018 | 11/13/2018 | 11/13/2018 | | PASS |
Andy J. Long
|
|
|
WIP on vertical construction for condos. Site imporovements and new sidewalks going in on ROW on Ash and River. Storm drains have sediment protection. No trackout or discharges observed.
|
General Inspection | 10/29/2018 | 10/29/2018 | 10/29/2018 | | PASS |
Michael Zawacki
|
|
|
Inspected 10/26. Site is clean, Ash st has been patched. Road work on river street. New lined washout built, foreman will make sure everyone used it.
|
General Inspection | 10/12/2018 | 10/12/2018 | 10/12/2018 | | PART |
Michael Zawacki
|
|
|
Paved entrance is mud covered, will be cleaned. Inspected 10/11 Entrance only being used for deliveries, have permission to park in lot across street. Site drainage worked during rain event, no standing water. No trackout or discharges.
|
General Inspection | 9/27/2018 | 9/27/2018 | 9/27/2018 | | PASS |
Andy J. Long
|
|
|
WIP on frame of apt buildings. Road work complete. Area has been swept. Approved
|
General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 | | PEND |
Andy J. Long
|
|
|
road work and stockpiles in ROW. Dry weather, no discharges. Entrance to River is blocked off. DI protected.
Folllow up scheduled on main site permit to check on post construction clean up of loose dirt.
|
Permit Ready to Issue | | | 5/4/2018 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 5/4/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/22/2018 | | 3/22/2018 | | DONE |
Andy J. Long
|
|
|
SWPPP with narrative and site map approved, RP not yet designated. Site preparation inspection required.
|
Application received | | | 12/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 7 2017 3:19PM
|