General Inspection | 12/18/2018 | 12/18/2018 | 12/18/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Michael Zawacki
|
|
|
|
Site Preparation | 11/30/2018 | 12/3/2018 | 12/3/2018 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/27/2018 | 11/27/2018 | 11/30/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/9/2018 | 11/9/2018 | 11/9/2018 | | PASS |
Michael Zawacki
|
|
|
Complete and landscaped. OK to final when building permit closed.
|
General Inspection | 10/25/2018 | 10/25/2018 | 10/25/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/10/2018 | 10/10/2018 | 10/10/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/14/2018 | 8/14/2018 | 8/14/2018 | P | PASS |
Michael Zawacki
|
|
|
Landscapers on site, causing some trackout onto sidewalk with skid steer. Stucco crew on site.
|
Random Inspection | 5/24/2018 | 5/24/2018 | 5/24/2018 | P | PART |
Michael Zawacki
|
|
|
WIP. Site is mostly clean and contained. Pile of gravel stored on sidewalk and road, lots of dirt washing away. Has gator guard around it but not working to well.
|
Issue & PRINT permit SFD | | | 1/17/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 1/12/2018 | | 1/12/2018 | | DONE |
Andy J. Long
|
|
|
ESC plan with site map and narrative approved.
|
Application received | | | 12/28/2017 | | |
|
|
|
|