Site Final | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | PASS |
Michael Zawacki
|
|
|
Call me if you need access to the site. Gate is locked. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
|
General Inspection | 1/23/2019 | 1/23/2019 | 1/23/2019 | | DONE |
Michael Zawacki
|
|
|
No activity, gate was locked.
|
General Inspection | 11/27/2018 | 11/27/2018 | 11/27/2018 | | PASS |
Michael Zawacki
|
|
|
Training area looks complete. Rock entrance still at site, no issues.
|
General Inspection | 10/11/2018 | 10/11/2018 | 10/11/2018 | | PASS |
Michael Zawacki
|
|
|
Met with foreman on site. Entrance is off Franklin, crushed rock entrance in place, some people have been driving around it, said they will make sure everyone uses it. Multiple washouts for mortar on site. All materials stored cleanly, no trash on site. Activity is on active traing grounds.
|
Routing - Erosion and Sediment | 7/25/2018 | | 7/25/2018 | | DONE |
Andy J. Long
|
|
|
New project submitted for parcel, this ESC permit will cover construction under BLD18-02304.
|
Change Status (ISS) | | | 7/17/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 7/17/2018 | | 7/17/2018 | | DONE |
Andy J. Long
|
|
|
ESC permit for Idaho Power Boise Operations Center . GRD17-00089 scope of work is complete and finaled. RP-PD to submit updated plans for proposed construction. No buildings approved under this permit.
|
Site Final | 5/21/2018 | 5/22/2018 | 5/22/2018 | A | PASS |
Michael Zawacki
|
|
|
Kyle -please call ahead Phone #: ###-####
|
General Inspection | 4/10/2018 | 4/10/2018 | 4/10/2018 | P | PASS |
Michael Zawacki
|
|
|
Eldon with Idaho Power is taking care of SWPPP. Knife River on site grading. Rock entrance going out to Franklin is installed. WHen they start running haul trucks they are going to exit through Idaho Power complex to keep tracking off ACHD roads and avoid running trucks head to head.
|
Site Preparation | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PASS |
Andy J. Long
|
|
|
Site walk through with RP Eldon.
Heavy duty rock construction entrance installed, DI protection on south side of Franklin (may be for ITD/ACHD road project per Eldon). No concrete or cement work for project, will be Idaho Power training yard and linemen practice area. Project is to be from February - May/June. Fugitive dust control may be required during import of material and grading.
Approved for construction.
Perimter silt fence properly installed.
|
Issue & PRINT permit COM | | | 2/15/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 1/3/2018 | | 1/3/2018 | | DONE |
Andy J. Long
|
|
|
ESC plan/SWPPP approved. Certified stormwater team designated. Site preparation inspection required.
|
Application received | | | 12/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 29 2017 10:04AM
|