Site Final | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PASS |
Andy J. Long
|
|
|
Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
Site cleaned, stabilized, and temp. BMPs removed. ESC permit finaled
|
Site Preparation | 1/10/2018 | 1/11/2018 | 1/11/2018 | P | PASS |
Michael Zawacki
|
|
|
Currently contractor is marking out utilities. Area will need inlet protection on road.
|
Issue & PRINT permit COM | | | 1/8/2018 | | DONE |
|
|
|
|
Application received | | | 1/5/2018 | | |
|
|
|
|
Routing - Erosion and Sediment | 1/5/2018 | | 1/5/2018 | | DONE |
Michael Zawacki
|
|
|
|
Permit Ready to Issue | | | 1/5/2018 | | DONE |
|
|
|
Met
|
Telephone call | | | 1/5/2018 | | DONE |
|
|
|
Left message stating the permit is ready and what fees are due
|