Site Final | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PASS |
Andy J. Long
|
|
|
Parking lot complete. Staging areas have revegetated with no loose sediment around site. No temp. BMPs left behind.
|
General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Michael Zawacki
|
|
|
Parking lot complete and landscaped. Area where job trailer was and off to side of project still bare.
|
General Inspection | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | PASS |
Michael Zawacki
|
|
|
Parking lot is paved, curbing in place. Workers are currently placing soil for landscaping prep. Large stockpile is on site. No ESC issues.
|
Random Inspection | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Michael Zawacki
|
|
|
Working on curbing. No ESC issues.
|
Random Inspection | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Michael Zawacki
|
|
|
Perimeter BMPs in place. Construction entrance with geotextile liner in place. Grading has begun.
|
Issue & PRINT permit COM | | | 4/9/2018 | | DONE |
|
|
|
|
Application received | | | 1/17/2018 | | |
|
|
|
|