Site Final | 5/16/2019 | 5/17/2019 | 5/21/2019 | P | PASS |
Michael Zawacki
|
|
|
|
Aging Inspection | 5/16/2019 | 5/16/2019 | 5/16/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
Aging Inspection | 3/14/2019 | 3/14/2019 | 3/14/2019 | | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 1/10/2019 | 1/10/2019 | 1/10/2019 | | PASS |
Michael Zawacki
|
|
|
Home is prepped for stucco. Trash is contained, no mud leaving site.
|
BMP Violation | 5/25/2018 | 5/29/2018 | 5/30/2018 | P | FAIL |
Michael Zawacki
|
|
|
No new washout, current washout is nearly overflowing.
|
BMP Violation | 5/24/2018 | 5/24/2018 | 5/25/2018 | P | FAIL |
Andy J. Long
|
|
|
No new concrete washout. No spillage from current washout but it is over 75% full. should dry out this weekend.
|
BMP Violation | 5/21/2018 | 5/22/2018 | 5/22/2018 | P | FAIL |
Andy J. Long
|
|
|
No new washout. Observed concrete truck driver use HHS washout container.
Final correction request to get a new washout by end of day tomorrow. Should be properly lined, marked with a sign, and have construction rock entrance to prevent trackout.
|
BMP Violation | 5/18/2018 | 5/22/2018 | 5/21/2018 | A | PEND |
Andy J. Long
|
|
|
concrete washout
RP stated the AM new washout has been ordered and will be installed. No trackout or use of full washout occuring.
Compliance extension to 5/22 PM
|
BMP Violation | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | FAIL |
Andy J. Long
|
|
|
Washout full. Reportedly using other sites washout without permission and causing track out.
Correction request to provide new concrete washout, post washout sign for Blackrock, and clean up old washout. New washout should have construction entrance.
|
Permit Ready to Issue | | | 2/27/2018 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 2/27/2018 | | DONE |
|
|
|
|
Application received | | | 2/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 13 2018 11:15AM
|