Site Final | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PASS |
Andy J. Long
|
|
|
behind Mcdonalds on Fairview Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
No ESC corrections needed. Permit finaled.
|
Site Preparation | 4/17/2018 | 4/18/2018 | 4/18/2018 | A | PASS |
Michael Zawacki
|
|
|
Phone #: ###-#### Inspection requested via web by Eldon Oyadomari. Spoke with Earth Energy on site. Bore is across parking lot, they will sweep as needed at exit pit as needed. Irragation line in way, Idaho Power may need to slightly modify bore plan to go under. Equipment being staged in empty parking lot behind McDonalds.
|
Issue & PRINT permit COM | | | 4/9/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/4/2018 | | 4/6/2018 | | DONE |
Michael Zawacki
|
|
|
Horizontal boring. No site prep required.
|
Telephone call | | | 4/6/2018 | | DONE |
Christina Prado
|
|
|
Called Eldon to advise permit is ready for pick up and gave fees due
|
Permit Ready to Issue | | | 4/6/2018 | | DONE |
Christina Prado
|
|
|
All met
|
Application received | | | 4/4/2018 | | |
|
|
|
|