Site Final | 4/19/2019 | 4/22/2019 | 4/26/2019 | P | PASS |
Andy J. Long
|
|
|
Home landscaped. Site cleaned up. Subdivsion BMPs to remain installed for ongoing construction. ESC permit conditions satisfied.
|
General Inspection | 4/18/2019 | 4/18/2019 | 4/19/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 3/29/2019 | 3/29/2019 | 3/29/2019 | | PASS |
Michael Zawacki
|
|
|
Landscapers on site.
|
General Inspection | 3/14/2019 | 3/14/2019 | 3/15/2019 | | PEND |
Michael Zawacki
|
|
|
Site walk through completed. Will write up report and share with RP and all builders. No major issues at site.
|
General Inspection | 6/29/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/15/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Michael Zawacki
|
|
|
Post rain inspection. Site free from runoff and rain caused issues.
|
Site Preparation | 5/14/2018 | 5/15/2018 | 5/15/2018 | A | PASS |
Andy J. Long
|
|
|
John Phone #: ###-####
Initial BMPs installed. Perimter gatorguard wattles installed below excavation area at toe of slope on lot. Permit sign posted. WIP on excavation.
Corrections requested for next inspection: - will need stabilized entrance/access post excavation. - properly stake in wattles at corner of site by portapot. - secure portapot for wind/vandals with rebar - provide trash or can for concrete & foundation guys.
|
Issue & PRINT permit SFD | | | 5/14/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/1/2018 | | 5/1/2018 | | PASS |
Andy J. Long
|
|
|
ESC site map and narrative approved. ESC site preparation inspection is required.
|
Application received | | | 4/20/2018 | | |
|
|
|
|