Site Final | 4/1/2019 | 4/3/2019 | 4/4/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 3/29/2019 | 3/29/2019 | 4/1/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final.
|
General Inspection | 8/21/2018 | 8/21/2018 | 8/21/2018 | A | PASS |
Michael Zawacki
|
|
|
Canal has been tiled. Retaing wall completed, currently shooting grade on top. Area excavated and lined with geotextile and waiting for gravel fill. All disturbances are contained, no esc issues.
|
Site Preparation | 7/6/2018 | 7/6/2018 | 7/6/2018 | A | PASS |
Andy J. Long
|
|
|
rick ###-#### 11 AM
Onsite conference. North border is a grassy area, no receiving waters or storm water drains. Approved not using wattle but preserving clearing limits and grass. Will check after initial work for additional BMPs.
Approved for construction.
|
Issue & PRINT permit COM | | | 6/29/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/13/2018 | | 6/13/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan resubmitted with correct plan size 11 x17. ESC plan approved. Certified RP designated.
|
Routing - Erosion and Sediment | 6/12/2018 | | 6/12/2018 | | FAIL |
Andy J. Long
|
|
|
site map illegible, only showing half of plan and half of construction details for BMPs.
|
Application received | | | 5/9/2018 | | |
|
|
|
|