Site Final | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Michael Zawacki
|
|
|
I removed DI bag and left on grass at park.
|
Site Final | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 11/20/2019 | 11/20/2019 | 11/20/2019 | | CANC |
Andy J. Long
|
|
|
|
Site Final | 9/17/2019 | 9/23/2019 | 9/23/2019 | P | NR |
Andy J. Long
|
|
|
check for DI bags in sub left by CBH Two DI bags located on Ardyce in front of 12022. Very close to the small neighborhood park.
Notified CBH RP Colby via text.
|
Site Final | 8/30/2019 | 9/17/2019 | 9/17/2019 | P | CANC |
Andy J. Long
|
|
|
rescheduled
|
Site Final | 8/27/2019 | 8/29/2019 | 8/30/2019 | P | PEND |
Andy J. Long
|
|
|
check for any remaining construction and request that all temporary BMPs (DI bags) be removed from Dropzone subdivsion.
|
Aging Inspection | 8/27/2019 | 8/27/2019 | 8/27/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
Site Preparation | 8/30/2018 | 8/30/2018 | 8/31/2018 | P | DONE |
Michael Zawacki
|
|
|
Tight lot between two existing homes. Will need perimeter controls, nothing preventing dirt from falling on neighboring lots. Dust will be an issue while backfill being removed, will need to watch track out onto common driveway.
|
Permit Ready to Issue | | | 8/29/2018 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 8/29/2018 | | DONE |
|
|
|
|
Application received | | | 7/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 16 2018 3:16PM
|