Site Final | 1/27/2020 | 1/30/2020 | 2/3/2020 | P | PASS |
Michael Zawacki
|
|
|
All homes completed and stable, all individual esc permits closed. Still some workers coming and going at site.
|
General Inspection | 1/27/2020 | 1/27/2020 | 1/27/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/26/2019 | 12/26/2019 | 12/26/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2019 | 11/25/2019 | 11/26/2019 | | PASS |
Andy J. Long
|
|
|
All homes on Cranberry are near completion. No corrections requested.
|
General Inspection | 10/25/2019 | 10/25/2019 | 10/28/2019 | | PART |
Michael Zawacki
|
|
|
All homes completed exteriors, landscapers on site. Pallets of sod on sidewalk, lots of tracked topsoil on street. Need to sweep when landscapers done.
|
General Inspection | 9/24/2019 | 9/24/2019 | 9/24/2019 | | PASS |
Michael Zawacki
|
|
|
All homes framed and in different stages of completion. Some homes still need driveways, washout still on site. Every home has its own trash box. Most homes landscaped. Street looks like it has been recently swept. No issues at site.
|
General Inspection | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | FAIL |
Michael Zawacki
|
|
|
Landscapers have topsoil and rocks stored on road, lots of tracking everywhere. Rollpan on site and being used. Some builders better at keeping clean site.
|
General Inspection | 8/8/2019 | 8/12/2019 | 8/12/2019 | P | PART |
Michael Zawacki
|
|
|
Individual building lots have trash containment and are no bad. All workers parked on street, some dirt street needs to be swept when everyone is off site.
|
General Inspection | 8/8/2019 | 8/8/2019 | 8/8/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Andy J. Long
|
|
|
Subdivision development/infrastucture complete. New SFHs now in progress on Cranberry. BMPs installed. No corrections requested.
|
General Inspection | 7/4/2019 | 7/4/2019 | 7/5/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/31/2019 | 6/3/2019 | 6/3/2019 | P | PART |
Michael Zawacki
|
|
|
Work on foundations and homes has begun. Roll pan washout on site. Some dirt on street and sidewalks from filling of backfill.
|
General Inspection | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | FAIL |
Michael Zawacki
|
|
|
New Owner Site is being used as dump, sent message and pictures to new owner.
|
General Inspection | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Michael Zawacki
|
|
|
Site prep work completed. Road paved, curb gutter and sidewalk installed. No home building has begun.
|
General Inspection | 10/10/2018 | 10/10/2018 | 10/10/2018 | P | PASS |
Michael Zawacki
|
|
|
Curbing finished, sidewalk about half complete. Grader on site getting road bed prepped for paving. Road will need to be swept when equipment removed.
|
General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Michael Zawacki
|
|
|
No current activity. Site will need a proper construction entrance before building.
|
General Inspection | 8/22/2018 | 8/27/2018 | 8/27/2018 | A | PASS |
Michael Zawacki
|
|
|
Sidewalk has been swept, area of sidewalk across street has been removed, area marked for utilities. Yards with flood irragation have been bermed off to prevent water from flowing onto and through job site. Permits are posted on telephone pole inside site.
|
General Inspection | 8/21/2018 | 8/22/2018 | 8/22/2018 | A | PART |
Andy J. Long
|
|
|
follow up to complaint response
Street sweeper has visited site as requested, but there is still additional corrections.
- sweep sidewalks with push brooms across street - install sediment protection on storm drain on McMillan - continue improvements to prevent irrigation water from flowing into site from adjacent yard to the south of entrance - relocate an ESC permit sign or SWPPP at entrance to site.
Talked to RP who said he will get it done. Follow up inspection on Monday.
|
Complaint Inspection | 8/21/2018 | 8/21/2018 | 8/21/2018 | P | PEND |
Andy J. Long
|
|
|
Flood irrigation flowed onto site causing muddy discharge and trackout to Farrow.
RP is working with homeowner to fix/contain the flood irrigation. Street sweeper scheduled for tomorrow AM. Rock construction entrance is reportedly installed.
Follow up scheduled.
|
Permit Ready to Issue | | | 8/6/2018 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 8/6/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 7/20/2018 | | 7/20/2018 | | DONE |
Michael Zawacki
|
|
|
Inspection required before excavation for neighborhood begins. No inspection required for demo.
|
Application received | | | 7/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2018 10:00PM
|