Site Final | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | PASS |
Andy J. Long
|
|
|
scheduled by Brad with RRC.
Project complete. DI bag in parking lot storm drain was removed per Brad
Work complete. DI bag removed. Approved.
|
Site Preparation | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | PASS |
Andy J. Long
|
|
|
Brad Phone #: ###-####
DI in parking lot is protected. RP will pull at end of project. Stormwater contained onsite, minimal earthwork.
Approved.
|
Issue & PRINT permit COM | | | 8/22/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/20/2018 | | 8/21/2018 | | DONE |
Andy J. Long
|
|
|
ESC plan approved. Certified RP. Please schedule ESC site preparation inspection.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/21/2018 | | DONE |
|
|
|
met
|
Telephone call | | | 8/21/2018 | | DONE |
|
|
|
Left Voicemail for Brad to inform him the permit is ready to be picked up
|
Application received | | | 8/20/2018 | | |
|
|
|
|