Site Final | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Andy J. Long
|
|
|
Construction complete. No disturbed area, no temporary BMPs left on site.
|
Aging Inspection | 10/23/2019 | 10/23/2019 | 10/24/2019 | | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 8/23/2019 | 8/23/2019 | 8/26/2019 | | PASS |
Andy J. Long
|
|
|
No issues at site, BLD still open. Will keep ESC open for now.
|
BMP Violation | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | CANC |
Andy J. Long
|
|
|
|
BMP Violation | 10/9/2018 | 10/11/2018 | 10/11/2018 | A | PASS |
Andy J. Long
|
|
|
Trash container now on site as requested. No trackout or discharges. Approved.
|
Random Inspection | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | FAIL |
Andy J. Long
|
|
|
Muddy discharge to gutter on Rim from site.
No perimeter sediment controls, no sediment protection on storm drain @ NE corner of Rim and Garden.
Correction request to fix ASAP and install BMPs as needed. RP-GC Brett stated he will be there within the hour to fix.
|
Issue & PRINT permit SFD | | | 8/28/2018 | | DONE |
|
|
|
|
Application received | | | 8/24/2018 | | |
|
|
|
|