Site Final | 5/28/2019 | 5/28/2019 | 5/28/2019 | P | PASS |
Andy J. Long
|
|
|
BLD finaled, home landscaped. No temporary BMPs to removed. ESC permit finaled.
|
General Inspection | 12/10/2018 | 12/19/2018 | 12/19/2018 | P | PASS |
Michael Zawacki
|
|
|
Foundation poured, kiddie pool used for a washout. All workers are parking on road. Back fill stored on neighboring lot.
|
Conference | 11/30/2018 | 12/3/2018 | 12/10/2018 | A | DONE |
Andy J. Long
|
|
|
Email warning about concrete washout sent to all Panamint sub homebuilders 12/10. Shilo, Caliper, Downey, and Stylish Homes
|
Permit Ready to Issue | | | 11/6/2018 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 11/6/2018 | | DONE |
|
|
|
|
Application received | | | 9/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 22 2018 3:58PM
|