Site Final | 9/24/2019 | 9/25/2019 | 9/25/2019 | P | PASS |
Michael Zawacki
|
|
|
check for DI bags and other temporary BMPs
|
General Inspection | 9/24/2019 | 9/24/2019 | 9/24/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 7/30/2019 | 7/30/2019 | 7/30/2019 | | PASS |
Michael Zawacki
|
|
|
Landscapers on site. Building exterior and drives looks completed. Sidewalk looks like it has been swept.
|
General Inspection | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Michael Zawacki
|
|
|
WIP on framing. Stabalized entrance and exits in alley and on Broadway.
|
General Inspection | 3/11/2019 | 3/19/2019 | 3/22/2019 | P | PASS |
Michael Zawacki
|
|
|
Still dewatering, very clean. No trackout to Broadway or alley.
|
General Inspection | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PASS |
Michael Zawacki
|
|
|
Discharge is .41 NTU. No issues at site.
|
Site Preparation | 3/7/2019 | 3/8/2019 | 3/11/2019 | P | CANC |
Andy J. Long
|
|
|
rescheduled
|
Site Preparation | 3/11/2019 | 3/11/2019 | 3/11/2019 | A | PASS |
Andy J. Long
|
|
|
Mark w/ Wright Bros (mid afternoon)
Rock construction entrance installed for Broadway access. ESC permit signs posted. Trucks to pull in off Broadway and exit via alley. Request for regular sweeping of the paved stretch of alley (north and south are dirt/gravel).
Dewatering for basement excavation is in progress. Water is clear and well point hose is connected to dewatering tank with baffles.
Reviewed concrete washout requirements. Follow up inspection scheduled.
|
Site Preparation | 3/6/2019 | 3/7/2019 | 3/7/2019 | P | CANC |
Andy J. Long
|
|
|
rescheduled
|
Issue & PRINT permit COM | | | 2/19/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/27/2018 | | 9/27/2018 | | DONE |
Michael Zawacki
|
|
|
met - RP needed before ground disturbing activities. Site prep inspection required.
|
Application received | | | 9/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 26 2018 8:14AM
|