General Inspection | 8/23/2019 | 8/23/2019 | 8/23/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 11/7/2018 | 11/7/2018 | 11/8/2018 | P | PASS |
Michael Zawacki
|
|
|
Pathway is almost all cut out, no paving yet. Buffer on each side, no trackout to warm springs.
|
Issue & PRINT permit COM | | | 10/29/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/12/2018 | | 10/15/2018 | | DONE |
Michael Zawacki
|
|
|
Multiple locations for access improvements. Please specify location for inspection when needed.
|
Permit Ready to Issue | | | 10/15/2018 | | DONE |
|
|
|
met
|
Telephone call | | | 10/15/2018 | | DONE |
|
|
|
Left voicemail for Jeff to inform him the permit is ready and what fees are due.
|
Application received | | | 10/12/2018 | | |
|
|
|
|