Site Final | 10/16/2019 | 10/16/2019 | 10/18/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/16/2019 | 10/16/2019 | 10/16/2019 | | CANC |
Andy J. Long
|
|
|
|
Site Final | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | NR |
Michael Zawacki
|
|
|
Side lot still bare.
|
General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 | | CANC |
Andy J. Long
|
|
|
|
Issue & PRINT permit SFD | | | 1/10/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 12/6/2018 | | 12/6/2018 | | PASS |
Michael Zawacki
|
|
|
Hillside requirements waived by engineering, no disturbances in hillside zone. Plan waiver request has been ok'd.
|
Application received | | | 11/6/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2018 9:31AM
|