Site Final | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Andy J. Long
|
|
|
Work complete, disturbed area stabilized, no temporary BMPs left behind.
|
General Inspection | 9/27/2019 | 9/27/2019 | 10/1/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/17/2019 | 4/25/2019 | 4/25/2019 | P | PASS |
Michael Zawacki
|
|
|
Concrete crew on site prepping to lay floor. Kiddie pool washout on site. Staging area on parking lot. Construction area has buffers on each side. No ESC issues.
|
General Inspection | 4/15/2019 | 4/16/2019 | 4/17/2019 | A | PASS |
Andy J. Long
|
|
|
project already started. No site prep requested.
BMPs installed. RP also in charge at Hawthorne and we reviewed ESC site preparation requirements.
|
Issue & PRINT permit COM | | | 3/4/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 11/23/2018 | | 11/23/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified PD; RP tbd once contract is awarded. ESC Site preparation inspection is required at the beginning of the project.
|
Application received | | | 11/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 12 2018 8:40AM
|