General Inspection | 9/30/2019 | 9/30/2019 | 9/30/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 6/17/2019 | 6/17/2019 | 6/19/2019 | P | PASS |
Michael Zawacki
|
|
|
Work area is below grade of curb and sidewalk. Entrances are paved, no issues.
|
Site Preparation | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Michael Zawacki
|
|
|
Superintendant not on site. Site is below grade, no ESC issues. Gates were locked, did perimeter walk.
|
General Inspection | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | CANC |
Andy J. Long
|
|
|
|
Permit Ready to Issue | | | 4/1/2019 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 4/1/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 12/7/2018 | | 12/7/2018 | | DONE |
Michael Zawacki
|
|
|
Valid RP needed prior to ground disturbing activities.
|
Application received | | | 11/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 21 2018 2:14PM
|