DOC - Permit Finaled | 4/6/2020 | 4/6/2020 | 4/6/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 3/23/2020 | 3/23/2020 | 3/23/2020 | | PASS |
Michael Zawacki
|
|
|
Lawnco on site installing irragation.
|
General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 | | PASS |
Michael Zawacki
|
|
|
Still needs landscaping.
|
General Inspection | 2/20/2020 | 2/20/2020 | 2/20/2020 | | PASS |
Michael Zawacki
|
|
|
Perimeter has gatorguard. Parking lot completed, still needs grass.
|
General Inspection | 2/5/2020 | 2/5/2020 | 2/6/2020 | | PASS |
Michael Zawacki
|
|
|
Needs revegetation.
|
General Inspection | 1/21/2020 | 1/21/2020 | 1/23/2020 | | PART |
Andy J. Long
|
|
|
Construciton is complete, area between parking lot and sidewalk is not yet stabilized/vegetated. No dirty runoff or material leaving site.
Perimeter control gator guard has been installed but is not properly staked and backfilled. Will notify RP.
|
General Inspection | 1/6/2020 | 1/6/2020 | 1/6/2020 | | PASS |
Michael Zawacki
|
|
|
Still needs landscaping.
|
General Inspection | 12/20/2019 | 12/20/2019 | 12/20/2019 | | PASS |
Michael Zawacki
|
|
|
Still needs landscaping.
|
General Inspection | 12/5/2019 | 12/5/2019 | 12/6/2019 | | PASS |
Michael Zawacki
|
|
|
Bricon on site spreading soil. Lot has perimeter control, no issues.
|
General Inspection | 11/15/2019 | 11/15/2019 | 11/15/2019 | | PASS |
Michael Zawacki
|
|
|
Curbing and paving completed. No landscaping has been started.
|
General Inspection | 10/31/2019 | 10/31/2019 | 10/31/2019 | | PASS |
Michael Zawacki
|
|
|
Lot graded and curbing done for parking lot. Two kiddie pools on site for washouts, no issues.
|
Permit Ready to Issue | | | 6/24/2019 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 6/24/2019 | | DONE |
|
|
|
|
VOIDED CHANGE STATUS | | | 2/14/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/14/2019 | | DONE |
|
|
|
Voide by accident
|
Routing - Erosion and Sediment | 2/6/2019 | | 2/6/2019 | | DONE |
Michael Zawacki
|
|
|
Void. Please use ESC19-00078, permit applied for with demo, not issued, still needs an RP before work begins.
|
Application received | | | 1/23/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2019 5:09PM
|