General Inspection | 10/31/2019 | 10/31/2019 | 10/31/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Michael Zawacki
|
|
|
|
Site Preparation | 1/31/2019 | 1/31/2019 | 1/31/2019 | A | PASS |
Andy J. Long
|
|
|
930 Matthew Falvey
Staging area setup. Two sites east and west of staging area. East site is out of water. End beam/cap to be installed, fill placed, and capped with sandstone steps.
West site is in water for end beam. Crew has turbidity curtain to surround work area. No fill, will place steps on existing material.
Track pads placed over grass to provide equipment access to Greenbelt. RP and project manager onsite. Permit posted.
|
Issue & PRINT permit COM | | | 1/29/2019 | | DONE |
|
|
|
|
Application received | | | 1/24/2019 | | |
|
|
|
|
Routing - Erosion and Sediment | 1/24/2019 | | 1/24/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Site map provided. Certified stormwater team designated. Site preparation inspection is required.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/24/2019 | | DONE |
|
|
|
met
|
Telephone call | | | 1/24/2019 | | DONE |
|
|
|
Spoke with Mathew to inform him the permit is ready and what fees are due.
|
Site Final | 4/4/2019 | 4/5/2019 | | A | |
Andy J. Long
|
|
|
|