Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberESC19-00117
StatusIssued
Name MELAINE ALDERSON
Site Address 924 W MCGREGOR CT
Project NameAce Co Precision
Customer Number 
ePlanReviewNo
Description
First phase of project completed under GRD18-00078/ESC18-01411. Construction entrance to prevent trackout, protect MS4 on Mcgregor, perimter sediment control, and fugitve dust control. SWPPP submitted and CGP 2017 NOI filed.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/13/20207/13/20207/13/2020 PASS
DetailsMichael Zawacki
Building exterior completed. Parking lot paved and landscaping done. Old storage lot has been graded. No issues at site.
General Inspection5/11/20205/11/20205/11/2020 CANC
DetailsAndy J. Long
General Inspection3/10/20203/10/20203/11/2020 PASS
DetailsMichael Zawacki
Site contained, no issues. WIP on concrete walls.
General Inspection1/7/20201/7/20201/7/2020 CANC
DetailsMichael Zawacki
General Inspection11/7/201911/7/201911/7/2019 CANC
DetailsMichael Zawacki
Issue & PRINT permit COM  6/18/2019 DONE
Routing - Erosion and Sediment2/11/2019 2/11/2019 PASS
DetailsAndy J. Long
SWPPP approved, certified stormwater team designated.
Application received  2/4/2019 DONE
Application submitted via PDS Online on Feb 4 2019 3:58PM