Site Final | 11/8/2019 | 11/8/2019 | 11/13/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 11/8/2019 | 11/8/2019 | 11/8/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Michael Zawacki
|
|
|
Exterior completed, no ground disturbances, no loose trash.
|
Site Preparation | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | PASS |
Andy J. Long
|
|
|
Jake ###-####
Building addition within existing mill compound. Perimeter paving and hardscaping to remain and will be used for stabilized construction access. Onsite stormdrain has been fitted with sediment protection. No MS4 inlets in area. Washout containment will be installed with the old loading ramp.
Approved for construction.
|
Issue & PRINT permit COM | | | 4/25/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/4/2019 | | 3/4/2019 | | DONE |
Michael Zawacki
|
|
|
Site prep inspection required.
|
Application received | | | 2/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 11 2019 4:34PM
|